What should you do?

You are a project manager who uses Project Professional 2013.
You need to change the default for all new projects so that tasks will be created in Auto Scheduled mode.
What should you do?
A. For each new project, use the Status Bar to set new tasks to be auto scheduled.
B. For each new project, use the Auto Schedule button on the Tasks tab.
C. Open the Global.mpt and use the Auto Schedule button on the Tasks tab.
D. Set the Default task type to Auto Scheduled for All New Projects in the Schedule Options.
E. Set the New tasks created option to Auto Scheduled and set the Schedule Options to All New Projects.

microsoft-exams

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.