A business analyst is documenting the acceptance criteria to support a minor modification in a user portal. The analyst submits the criteria for review, but it is deemed incomplete and returned.
What could have caused the documentation to be returned?
A. The analyst did not include the scope document in the acceptance criteria paperwork.
B. The analyst utilized user stories as a requirements document tool.
C. The analyst failed to gather any baseline information.
D. The analyst performed forward and backwards traceability.