A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch. The business analyst tells the stakeholder that the requirement status was changed to “deferred”.

A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch. The business analyst tells the stakeholder that the requirement status was changed to “deferred”.
What could have prevented the stakeholder from being surprised about the status change?
A. The status should have been reviewed prior to project launch.
B. The status should have been communicated to all project stakeholders.
C. The status should have been updated in the traceability matrix.
D. The status should have been communicated to the requirement’s source.