Testing on a project has been completed. In order to proceed with deployment, a decision is needed.

Testing on a project has been completed. In order to proceed with deployment, a decision is needed.
Who should the business analyst contact to review the testing results and get approval to proceed with deployment?
A. The tester identified in the testing strategy
B. The project manager identified in the project charter.
C. The project sponsor identified in the scope document.
D. The person identified in the RACI matrix.