Company A is working on implementing a new platform with multiple stakeholders. The business analyst has gathered the requirements and established a baseline. However, scope creep is a persistent problem.

Company A is working on implementing a new platform with multiple stakeholders. The business analyst has gathered the requirements and established a baseline. However, scope creep is a persistent problem.
What could the business analyst have established to help manage this situation?
A. Configuration management system
B. Sponsor signoff
C. Change control process
D. Communication plan

Download Printable PDF. VALID exam to help you PASS.

One thought on “Company A is working on implementing a new platform with multiple stakeholders. The business analyst has gathered the requirements and established a baseline. However, scope creep is a persistent problem.

  1. C. change control process … because it sets rules and structures for any changes in the baselines. so it can prevent scope creeo