The sales team of a company has won a time-and-material project. The business analyst discovers that the sales team has underestimated the required budget and schedule.

The sales team of a company has won a time-and-material project. The business analyst discovers that the sales team has underestimated the required budget and schedule.
Which course of action should the business analyst take?
A. Accept the contract, and deliver only the requirements that fit within the budget and schedule
B. Develop a requirements baseline document and use it to negotiate the scope in the contract.
C. Refrain from working on the project and request that the customer cancel the contract.
D. Accept the contract, and then notify the customer about the potential for a cost overrun.