During user acceptance testing, a defect is logged by a user from a department that did not participate in the requirements analysis. To avoid this situation and minimize impact on the project, the user should have been:

During user acceptance testing, a defect is logged by a user from a department that did not participate in the requirements analysis. To avoid this situation and minimize impact on the project, the user should have been:
A. interviewed to understand how the user’s work would be impacted.
B. involved in the development and sign-off of the business requirements.
C. given the opportunity to review the user acceptance test scripts.
D. identified as a stakeholder as part of the stakeholder analysis.