A stakeholder wants to modify an existing feature. Which of the following would be used to determine the scope of the change on the product?
A. Sequence diagram
B. Requirements traceability matrix
C. Requirements attributes table
D. Project schedule and cost baseline
Correct Answer: B
Explanation/Reference:
Reference: https://opentextbc.ca/projectmanagement/chapter/chapter-9-scope-planning-project-management/