Home » PMI » PMI-PBA » Several interviews with stakeholders to develop an inventory management system in a new architectural environment have revealed a significant concern about system and architectural stability. In which tool should the business analyst include this attribute to ensure that the requirement meets the acceptance criteria?
Several interviews with stakeholders to develop an inventory management system in a new architectural environment have revealed a significant concern about system and architectural stability. In which tool should the business analyst include this attribute to ensure that the requirement meets the acceptance criteria?
A. Traceability matrix
B. Interface analysis
C. Stakeholder satisfaction survey
D. Process modeling
Correct Answer: B
Explanation/Reference:
Reference: https://www.businessanalystlearnings.com/ba-techniques/2014/5/31/interface-analysis