A stakeholder has rejected a project’s deliverable because it does not meet the original business need. It is further determined that the deliverable does not meet the requirements identified in the baseline.
What is the best approach to resolve this issue?
A. Provide the stakeholder with a copy of the approved requirements baseline and move forward without making a change.
B. Meet with the customer can apologize for misunderstanding the business’s need.
C. Require development resources to work overtime to modify the deliverable to satisfy the stakeholder.
D. Suggest re-estimating the requirement and following the change control process.