Home » PMI » PMI-PBA » The business analyst wants to ensure that requirement changes can be formally tracked after the product is baselined. What will the business analyst need to evaluate the proposed change?
The business analyst wants to ensure that requirement changes can be formally tracked after the product is baselined. What will the business analyst need to evaluate the proposed change?
A. Scope statement
B. Impact analysis
C. Requirements management plan
D. Pareto analysis
Correct Answer: B
Explanation/Reference:
Download Printable PDF. VALID exam to help you PASS.
|
|