A project team has 120 days to deliver a solution, but the stakeholders have too many requirements for the delivery window. What requirements prioritization technique should be used to determine which requirements will be delivered?
A. Multivoting
B. MoSCoW
C. Time-boxing
D. Budget analysis
Correct Answer: B
Explanation/Reference:
Reference: https://www.modernanalyst.com/Resources/Articles/tabid/115/ID/3332/Techniques-to-Prioritize-Requirements.aspx
Download Printable PDF. VALID exam to help you PASS.
|
|
The correct response is C since it’s restricted by time / 120 Day (Time boxing)