A project was in the design phase when the team received news of a new regulatory mandate that affects the project. The requirements have already been approved and baselined. If the new requirements are not included, the company will be out of compliance and may face monetary penalties.
What should the business analyst do next?
A. Define the project scope
B. Obtain approval from the project manager.
C. Follow the change control process.
D. Update the requirements