A project that was ongoing well for the last few months has encountered a situation-regulatory authorities have deemed that the project does not meet their requirements. Although regulatory requirements were identified during an earlier phase of the project, there is no substantial evidence to prove that the requirements were formally rejected.

A project that was ongoing well for the last few months has encountered a situation-regulatory authorities have deemed that the project does not meet their requirements. Although regulatory requirements were identified during an earlier phase of the project, there is no substantial evidence to prove that the requirements were formally rejected.
This could have been avoided if:
A. the customer met with regulatory authorities to verify that their requirements were also considered.
B. a change control process for requirements and their statuses was followed.
C. the project manager circulated the meeting minutes after the discussions with all the attendees.
D. the project team documented customer requests and obtained sign-off.

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.