The business analyst receives multiple changes from different stakeholders during the requirements gathering phase of a project. How should the business analyst track the requirements throughout the lifecycle of the project to secure the delivery of the expected solution?

The business analyst receives multiple changes from different stakeholders during the requirements gathering phase of a project. How should the business analyst track the requirements throughout the lifecycle of the project to secure the delivery of the expected solution?
A. Record all the requirements in a matrix, review it regularly, and get approval from stakeholders.
B. Perform inspections through the lifecycle of the project to detect any gaps and adjust the requirements baseline.
C. Plan regular meetings with stakeholders to review the requirements baseline update and to discuss changes.
D. Establish a risk traceability matrix and designate someone to manage each risk with the appropriate response.

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.