A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements approval meeting. The stakeholder insists that these requirements must be taken into account despite time and budget constraints.

A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements approval meeting. The stakeholder insists that these requirements must be taken into account despite time and budget constraints.
What is the most effective way to manage this situation?
A. Postpone the baseline approval meeting, analyze the impact, and schedule a new meeting to discuss dependencies and priorities with stakeholders.
B. Share the new requirements with all stakeholders and ask them to submit their comments before the meeting.
C. Ask for more resources to manage this change and justify these additional resources with the value the change will give to the company.
D. Discuss the change with stakeholders during the baseline approval meeting and ask them to approve the new baseline.

Download Printable PDF. VALID exam to help you PASS.

2 thoughts on “A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements approval meeting. The stakeholder insists that these requirements must be taken into account despite time and budget constraints.

  1. I think that the B is not correct because it’ a day before the meeting and maybe the stakeholders can’t submit their comments in the short period of time.in addition, the BA must analyze the impact and if it is logical requirement , he would ask others to submit their attitudes…so I think as the requirement is critical, the best option is to postpone the meeting until the ba conduct further research. I think A is correct

    1. A. Postpone the baseline approval meeting, analyze the impact, and schedule a new meeting to discuss dependencies and priorities with stakeholders.