Two weeks prior to the delivery date, a customer changes the business requirements. What should the business analyst do?
A. Deliver the existing product and then begin work on the requested changes.
B. Ask the developers to implement the changes.
C. Trace the requirements and measure the impact of the requested changes on the existing delivery date.
D. Schedule a review by the change control board (CCB) to determine next steps.