The project team has all the document control process and versioning in place to capture the requirements changes. The team ensures that the change is documented in the scope document, resulting in the changed work breakdown structure (WBS) and schedule. However, a key requirement was not implemented in the release.

The project team has all the document control process and versioning in place to capture the requirements changes. The team ensures that the change is documented in the scope document, resulting in the changed work breakdown structure (WBS) and schedule. However, a key requirement was not implemented in the release.
Which is a possible reason why the requirement was not implemented?
A. The requirements management plan was not updated with the change.
B. The requirements traceability matrix was not updated with the change.
C. The scope management plan was not updated with the change.
D. The schedule management plan was not updated with the change.

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.