A new project’s goal is to replace an existing system. What is an input into solution evaluation and decision making in this context?

A new project’s goal is to replace an existing system. What is an input into solution evaluation and decision making in this context?
A. Cost-benefit analysis of the existing system
B. New solution design specification
C. Customer metrics on the existing system
D. Technical readiness of the development team

Download Printable PDF. VALID exam to help you PASS.