A project’s requirements baseline is established and approved. A stakeholder then submits a new requirement through the change control process.
How can the business analyst determine the impact on existing requirements?
A. Use time-boxing to defer the new requirement.
B. Review the requirements traceability matrix.
C. Update the use case documentation.
D. Perform a stakeholder analysis
B