Home » PMI » PMI-PBA » A business analyst is ready to begin requirements elicitation; however, stakeholders are not available to participate for another two weeks. Which elicitation technique should the business analyst use during this time?
A business analyst is ready to begin requirements elicitation; however, stakeholders are not available to participate for another two weeks. Which elicitation technique should the business analyst use during this time?
A. Brainstorming
B. Benchmarking
C. Document analysis
D. Cost-benefit analysis
Correct Answer: A
Explanation/Reference: