Projects have been managed well and completed on schedule and on budget. However, successful completion of the projects has not improved the company’s performance and profitability.

Projects have been managed well and completed on schedule and on budget. However, successful completion of the projects has not improved the company’s performance and profitability.
Which of the following should have been implemented to ensure that the projects would improve the company’s performance and profitability?
A. A risk plan
B. A strategies and goals analysis
C. A project management plan
D. A review with appropriate stakeholders