A new project is in the planning phase. The business owner believes that, since the timeline is aggressive, requirements elicitation should begin as soon as possible.

A new project is in the planning phase. The business owner believes that, since the timeline is aggressive, requirements elicitation should begin as soon as possible.
Which activity should the business analyst initiate before beginning requirements elicitation?
A. Draft a high-level data model.
B. Prepare the requirements traceability matrix.
C. Document how the relevant systems interact.
D. Define how the solution will be evaluated.