Which statement accurately depicts what changes can be made to requirements after they are baselined?
A. Requirements can be changed through a defined process.
B. Requirements cannot be changed once development begins.
C. Requirements cannot be changed once user acceptance testing begins.
D. Requirements can be changed only with sponsor approval.
Correct Answer: A
Explanation/Reference:
Explanation:
The main output is the scope baseline, which consists of three documents; the scope statement (including both project and product requirements), the WBS(s), and the WBS dictionary. These are reviewed and upon approval, the scope baseline is created. Once that baseline has been approved, changes can only be made through a change control procedure. The scope baseline will be used to continually compare the actual results and work being done on the project to the original, approved scope.