The document that defines the process for managing requirements revisions is the:
A. project management plan.
B. communications management plan.
C. scope management plan.
D. change management plan.
The document that defines the process for managing requirements revisions is the:
A. project management plan.
B. communications management plan.
C. scope management plan.
D. change management plan.
in my view correct answer is D. change management plan