Sprint burndown charts are an efficient tracking tool, because they show:
A. An estimate of the total work remaining for the Sprint.
B. How much effort has gone into a Sprint.
C. How many hours have been worked by each Development Team member.
D. How many Product Backlog items remain.
Correct Answer: A
Explanation/Reference: