Which statement best describes the Sprint Review? (Choose the best answer.)
A. It is used to congratulate the Development Team if it did what it forecast, or to punish the Development Team if it failed to meet its forecast.
B. It is a demo at the end of the Sprint for everyone in the organization to check on the work done.
C. It is a mechanism to control the Development Team’s activities during a Sprint.
D. It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next.
OPTION D is the right answer
The purpose of the Sprint Review is to inspect the outcome of the Sprint and determine future
adaptations. The Scrum Team presents the results of their work to key stakeholders and progress
toward the Product Goal is discussed.
OPTION D is the right answer
No need for the word or concept DEMO in scrum, as we re not trying to sell any software product during Sprint review. Also from exam point of view in above 4 options the term stake holders (presence) is mentioned in option 4. 🙂
Sprint review is a review meeting between the scrum team and the stakeholders to discuss how the sprint went, and what to do next.
Agree with D