During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?
A. When the Product Owner identifies new work.
B. As soon as possible after they are identified.
C. When the Scrum Master has time to enter them.
D. During the Daily Scrum after the Development Team approves them.
Correct Answer: B
Explanation/Reference:
How To Pass PSM I Exam?
Scrum PSM I PDF dumps.
High quality PSM I PDF and software. VALID exam to help you pass.
|
|
How To Pass PSM II Exam?
Scrum PSM II PDF dumps.
High quality PSM II PDF and software. VALID exam to help you pass.
|
|
Why not D?
Agree with B
A is right becasue here we are talking about new work or decomposition of work. Team only decompose first few stories in Sprint planning and after that as and when they progress they keep on decomposing the work and adding new work (Tasks) to the stories in the sprint. Adding new work here is not addition of new stories in the middle of the sprint.
Of course B is the right answer. No idea why there’s debate here.
Development teams are solely responsible for Sprint Backlog. So I think B is the right answer.
The anwser is A : When the Product Owner identifies new work.
B is correct, see discussion here: https://www.scrum.org/index.php/forum/scrum-forum/5519/during-sprint-when-new-work-or-further-decomposition-work-added-sprint
since when does the Product Owner identify work for the SPRINT backlog?