Why does the Product Owner want the Development Team to adhere to its definition of "Done"? (Choose the best answer.)
A. To have complete transparency into what has been done at the end of each Sprint.
B. To be able to reprimand the team when they don’t meet their velocity goal for the Sprint.
C. To know what the team will deliver over the next three Sprints.
D. To predict the team’s productivity over time.