For the purpose of transparency, when does Scrum say a new increment of working software must be available?
A. After the acceptance testing phase.
B. Before the release Sprint.
C. Every 3 Sprints.
D. At the end of every Sprint.
E. When the Product Owner asks to create one.
Correct Answer: D
Explanation/Reference: