How many possible paths are identified for this project?
The following is a network diagram for a project. How many possible paths are identified for this project? A. 3 B. 4 C. 6 D. 7
The following is a network diagram for a project. How many possible paths are identified for this project? A. 3 B. 4 C. 6 D. 7
Perform Quality Control is accomplished by: A. Identifying quality standards that are relevant to the project and determining how to satisfy them. B. Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes.…
An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as: A. Forecasting. B. Brainstorming. C. Historical databases. D. Cost of quality.
Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements? A. Develop Project Management Plan B. Develop Project Charter C. Direct and Manage Project Execution D.…
Completion of the product scope is measured against the product: A. prototypes B. requirements C. analyses D. benchmarks
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the: A. Project management plan. B. Project charter. C. Work breakdown structure. D. Stakeholder register.
A contract typically is used when a project is being performed for an external customer. An agreement is used as an input to. A. Develop project charter B. Develop project team C. Plan procurement management D. Conduct procurements
Which process determines the risks that may affect the project and documents their characteristics? A. Control Risks B. Plan Risk Management C. Plan Risk Responses D. Identify Risks
Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed? A. Resource breakdown structure B. Staffing management plan C. Project organizational chart D. Scope management plan
The scope management plan and scope baseline are contained in: A. organizational process assets B. a requirements traceability matrix C. the project charter D. the project management plan