Home » PMI » PMP » Work performance information in control risks means that
Work performance information in control risks means that
A. Recommended preventive or corrective action is considered through change requests
B. Outcomes of risk reassessments and risk audits are documented
C. Templates to the risk management plan and the risk register are recommended
D. A mechanism to communicate and support project decision making is provided
Correct Answer: D
Explanation/Reference:
Explanation:
All of the answers are outputs in the control risks process, however, work performance information specifically provides a mechanism to communicate and support project decision making.
How To Pass PMP Exam?
PMI PMP PDF dumps.
High quality PMP pdf and software. VALID exam to help you pass.
|
|
Download Printable PDF. VALID exam to help you PASS.
|
|