The key way for a project manager to promote optimum team performance in project teams whose members are not collocated is to.
A. Build trust
B. Establish a reward and recognition system
C. Obtain the support of the functional managers in the other locations
D. Exercise his or her right to control all aspects of the project
Correct Answer: A
Explanation/Reference:
Explanation:
Team members who are physically separate from one another tend not to know each other well. They have few opportunities to develop trust in the traditional way, and they tend to communicate poorly with one another. Trust then must become the foundation upon which all team-building activities are built.