To help limit conflict and misunderstandings concerning the justification, objectives, and high-level requirements of the project among your team members and their functional managers, you ask the project sponsor to prepare a___________

You are beginning a new project staffed with a virtual team located across five different countries. To help limit conflict and misunderstandings concerning the justification, objectives, and high-level requirements of the project among your team members and their functional managers, you ask the project sponsor to prepare a___________
A. Memo to team members informing them that they work for you now
B. Project charter
C. Memo to functional managers informing them that you have authority to direct their employees
D. Human resource management plan

How To Pass PMP Exam?

PMI PMP PDF dumps.

High quality PMP pdf and software. VALID exam to help you pass.

Download Printable PDF. VALID exam to help you PASS.

Posted in: PMP

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.