Home » PMI » PMP » Which of the following techniques may be applied to reevaluate the schedule?
A project manager needs to deliver the project 2 weeks before the planned date without changing the scope. Which of the following techniques may be applied to reevaluate the schedule?
A. What-if scenario analysis
B. Critical chain method
C. Schedule crashing
D. Resource leveling
Correct Answer: C
Explanation/Reference:
How To Pass PMP Exam?
PMI PMP PDF dumps.
High quality PMP pdf and software. VALID exam to help you pass.
|
|
Download Printable PDF. VALID exam to help you PASS.
|
|