Home » PMI » PMP » An input to the Identify Stakeholders process is:
An input to the Identify Stakeholders process is:
A. The project management plan.
B. The stakeholder register.
C. Procurement documents.
D. Stakeholder analysis.
Correct Answer: C
Explanation/Reference: