Home » PMI » PMP » However, you also know that quality control has costs associated with it and that the project has a limited budget. One way to reduce the cost of quality control is to___________
You recognize the importance of quality control on your project. However, you also know that quality control has costs associated with it and that the project has a limited budget. One way to reduce the cost of quality control is to___________
A. Work to ensure that the overall quality program is ISO compliant
B. Use statistical sampling
C. Conduct inspections throughout the process
D. Use trend analysis
Correct Answer: B
Explanation/Reference:
Explanation:
Statistical sampling uses part of a population to draw conclusions about the total population. It is a well-proven technique that can significantly reduce the cost of quality control.+