Review the following network diagram and table.
Of the various activities, which ones would you crash and in what order?
A. A, C, E, and F
B. A, B, D, and F
C. A, B, E, and F
D. C, A, F, and G
Correct Answer: D
Explanation/Reference:
Explanation:
First, it is necessary to determine the critical path, which is A, C, F, and G. To determine the lowest weekly crashing cost, start with C at $1,500 per week. The next activity is A, followed by F and G.