Home » PMI » PMP » By reviewing cumulative cost curves, the project manager can monitor_______
By reviewing cumulative cost curves, the project manager can monitor_______
A. EV
B. PV
C. CVs
D. CPI
Correct Answer: C
Explanation/Reference:
Explanation:
Cumulative cost curves, or S-curves, enable the project manager to monitor cost variances at a glance. The difference in height between the planned- expenditure curve and the actual-expenditure curve represents the monetary value of variances at any given time.