Home » PMI » PMP » The organizational process assets that are of particular importance to Plan Communications are:
The organizational process assets that are of particular importance to Plan Communications are:
A. Formal plans and procedures
B. Lessons learned and historical information
C. Guidelines and knowledge bases
D. Stakeholder positions and their influence
Correct Answer: B