Activity cost estimates are quantitative assessments of the probable costs required to:
A. Create WBS.
B. complete project work.
C. calculate costs.
D. Develop Project Management Plan.
Home » PMI » PMP » Activity cost estimates are quantitative assessments of the probable costs required to: