Which of the following is a key input to define activities?
A. Project management plan
B. Project scope management plan
C. Schedule management plan
D. Project management software
Correct Answer: C
Explanation/Reference:
Explanation:
While there are a number of inputs to define activities, the schedule management plan is a key input. It shows the level of detail necessary to manage the work.