You are conducting a stakeholder analysis on your project. Your organization uses an approach to classify stakeholders based on their level of authority and their active involvement in the project.

You are conducting a stakeholder analysis on your project. Your organization uses an approach to classify stakeholders based on their level of authority and their active involvement in the project.
This approach is known as____________
A. A power/interest grid
B. A power/influence grid
C. An influence/impact grid
D. A salience model