To anticipate and help develop approaches to deal with potential quality problems on your project, you want to use a variety of root-cause analysis techniques including all the following approaches EXCEPT____________

To anticipate and help develop approaches to deal with potential quality problems on your project, you want to use a variety of root-cause analysis techniques including all the following approaches EXCEPT____________
A. Fishbone diagrams
B. Ishikawa diagrams
C. System or process flowcharts
D. Checklists