To anticipate and help develop approaches to deal with potential quality problems on your project, you want to use a variety of root-cause analysis techniques including all the following approaches EXCEPT____________
A. Fishbone diagrams
B. Ishikawa diagrams
C. System or process flowcharts
D. Checklists
Correct Answer: D
Explanation/Reference:
Explanation:
Checklists are used to verify that the work of the project and its deliverables fulfill a set of requirements.