Home » PMI » PMP » An input to the Perform Quantitative Risk Analysis process is the:
An input to the Perform Quantitative Risk Analysis process is the:
A. quality management plan.
B. project management plan.
C. communications management plan.
D. schedule management plan.
Correct Answer: D
Explanation/Reference: