The first step in collecting requirements on any project, large or small, is to____________
A. Talk with the project stakeholders through interviews
B. Review the scope management plan
C. Conduct facilitated workshops with stakeholders
D. Prepare a requirements document template that you and your team can use throughout the collect requirements process
Correct Answer: B
Explanation/Reference:
Explanation:
The scope management plan is reviewed first as it provides clarity as to how the project team will determine which requirements need to be collected on the project.