Your company is embarking on a project to launch a new product delivery service. You are the project manager for this project and have just finished the concept phase. The various outputs/deliverable(s) for this phase include__________
A. Project management plan
B. Scope of work and requirements
C. Project charter and stakeholder register
D. Roles and responsibilities of the project manager
Correct Answer: C
Explanation/Reference:
Explanation:
The project charter signifies official sanction by top management and starts the planning, or development, phase. This document formally recognizes the existence of the project and provides the project manager with the authority to apply organizational resources to project activities. The stakeholder register is an output of identify stakeholders and also an output during the initiating processes.
How To Pass PMP Exam?
PMI PMP PDF dumps.
High quality PMP pdf and software. VALID exam to help you pass.
|
|
Download Printable PDF. VALID exam to help you PASS.
|
|