You and your team are documenting requirements on you project to control fatigue as people need to work more hours to keep up with the competition. You decided to set up components for the requirements on your project. Acceptance criteria are an example of_________
A. Stakeholder requirements
B. Transition requirements
C. Project requirements
D. Business requirements
Correct Answer: C
Explanation/Reference:
Explanation:
Various components of requirements documentation can be used. Examples are: business requirements, stakeholder requirements, solution requirements, project requirements, and requirements assumptions, dependencies, and constraints. Project requirements consist of acceptance criteria and levels of service performance, safety, and compliance.
How To Pass PMP Exam?
PMI PMP PDF dumps.
High quality PMP pdf and software. VALID exam to help you pass.
|
|
Download Printable PDF. VALID exam to help you PASS.
|
|