You are in the process of purchasing 67 desktop computers, monitors, and a standard desktop software package for an upcoming project. What type of contract will you likely use?
A. Purchase order
B. Fixed-price
C. Cost-plus-percentage of cost
D. Net 30
Correct Answer: A
Explanation/Reference: