Home » PMI » PMP » How closely the scope is being maintained relative to the scope baseline is contained within:
Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:
A. project documents updates.
B. project management plan updates.
C. change requests.
D. work performance information.
Correct Answer: D